Project description
• Voltage level:
220/110/22kV
• Power capacity: 1x125 MVA and
1x25 MVA
• 220kV side:
2 bays
• 110kV side:
6 bays
• 22kV side:
8 cubicles
This is one of the biggest power
transmission substations in the North,
connecting overhead lines to supply
electricity for Ninh Binh, Thai Binh,
Nam Dinh and Hai Phong provinces.
Innovation
This is the first power substation using a computerized substation control system (LSA) in Vietnam.
Customer
benefit
Customer vision of modern controlling concept in a power substation.
|